Bia Tiep Restaurant

  • Package : Construction and Finishing Works
  • Scale : 2 basements, 6 floors, Total slab area: 2.500 m2, construction area: 18.683 m²
  • Location : 198 Hoang Van Thu, W.9, Phu Nhuan District, HCM City
  • Client : Tay Nam Co., Ltd
  • Year : 2012
  • Progress : Completed
Photos Construction updates

On January 04, 2012, Tan Ky Construction Real Estate Trading Corporation signed a contract with Tay Nam Co., Ltd for the package “Construct the Bia Tiep Restaurant”.

 

 

-Total area: 2,500 m²
- Floor area: 18.683 m², 2 basements, 6 floors
- Location: 198 Hoang Van Thu, Phu Nhuan Dist, HCM City
- Commencement date: 11/02/2012
- Construction duration: 210 days.